The table below provides details of the budget changes between the 2025/26 adjusted budget and the proposed 2026/27 budget.

Budget Reconciliation

 

 

Inflation

 £'000

 £'000

Expenditure

 

 

Inflation related to Staffing costs

 733

 

Inflation related to the cost of Repairs & Maintenance for works and materials

 248

 

Inflation related to the cost of Housing Investment for works and materials

 78

 

Corporate inflation rates applied to other expenditure (including SSC’s)

 288

 

Total Expenditure Inflation

 

     1,347

Income

 

 

Rent Inflation

(3,312)

 

Service Charge inflation as per appendix 3

(164)

 

Leaseholder and other income

(158)

 

Total Income Inflation

 

(3,634)

Total Inflation

 

(2,287)

Service Investment

 £'000

 £'000

Expenditure

 

 

Repairs & Maintenance – increase in staffing resources for condensation and damp (Awaab’s Law), empty homes work and increase in legal resources for managing volume of disrepair claims.

           681

 

Housing Management & Support – increased cost of insurance premiums in respect of LPS blocks (excess layer insurance) and increased lease costs in relation to the Housing Centre.

           248

Housing Investment & Asset Management – external stock condition survey investment and additional funding required in respect of Building Safety.

        1,205

 

Council-owned Temporary Accommodation – increased costs reflecting the nature/scale of works required on these properties.

           200

 

Tenancy Services – introduction of a Home Ownership Pact to operate on a pilot basis for tenants of LPS blocks and increased fire safety resources.

           605

 

Capital Financing – increase in borrowing costs and depreciation charge

 2,749

 

LPS – increase in budget requirements for ongoing security costs and waste clearance.

           250

 

Housing Strategy & Supply – increased staffing resources for project management and IT to support regulatory compliance and quality assurance.

           160

 

Total Service Investment

 

   6,098

Other Changes

 £'000

 £'000

Expenditure

 

 

Repairs & Maintenance – Increase in capitalisation of responsive repair and empty homes works costs as a result of the nature of works undertaken.

(1,275)

 

Other Changes – Net reduction primarily in staffing budgets as a result of the decreased employer pension contribution rate (14.9%, compared to previous 19.8%).

(793)

 

 

 

(2,068)

Income

 

 

Increase in rental income from new supply delivered in 2025/26 and the part year impact of homes delivered in 2026/27.

(1,354)

 

Latest costs associated with leaseholder works is higher than budgeted for resulting in an increased income budget for 2026/27, this includes general increased costs of delivering repairs and maintenance.

(389)

 

 

 

(1,743)

Total Other Changes

 

(3,811)

Deficit / (Surplus)

 

0

 

A second table is also supplied which outlines the inflation rate assumptions providing further context to the budget proposals.

2026/27 Inflation Assumptions

 

Rent

4.80%

Salary

2.75%

Premises Repairs

4.00%

Other income

3.00%

Other expenditure

1.00%

 

Support Service Charges & other recharges

The table below provides a breakdown of the support service charges and other charges for 2026/27 and compares this to 2025/26. These are subject to change following a review and finalisation of charges as part of the General Fund Budget proposals. Any change will impact the bottom line revenue surplus and will impact the contribution to reserves, a reduction in revenue surplus will increase the borrowing requirement for 2026/27.

Charging Service

Adjusted Budget 2025/26 £'000

Budget 2026/27
£'000

Support Functions:

 

 

Insurance Costs

       1,713

       1,705

ICT

       1,073

      1,259

Finance

          416

          341

Legal & Democratic

       1,039

       1,284

Human Resources

          435

          479

Property

          218

          192

Procurement

          412

321

Business Operations

          101

174

Support Service Functions Total

       5,407

       5,754

Other charges:

 

 

Director

 283

          283

Tenancy Fraud

 137

          141

Youth Service

 255

          255

Discretionary Community Grants

 145

          145

Disabled Adaptations

 126

          130

Resident Involvement

 294

          404

Welfare Support

 82

           85

CCTV at LPS blocks

 294

          294

Housing Allocations

 399

          489

Apprenticeship Levy

 32

           32

Homing in and Area Panels

 31

           31

Other Charges Total

 2,078

       2,288

Total

 7,485

       8,042

 

 


 

Item

Estimated Balance as at 01/04/2025
£'000

Use during 2025/26

Estimated Balance as at 31/03/2026 £'000

Contribution (to) / from Reserves
£'000

Forecast use during 2026/27
£'000

Estimated Balance as at 31/03/2027 £'000

Conclusion

HRA Reserves

 

 

 

 

 

 

 

HRA Working Balance

(3,000)

                      

(3,000)

 

 

(3,000)

A minimum working balance of £3m is recommended by the Chief Finance Officer in accordance with the requirements of Section 25 of the Local Government Act 2003. 

HRA General Reserves

(7,657)

846

(6,811)

1,000

 

(5,863)

General reserves balance set aside to deal with any unexpected costs in year.

Repairs & Maintenance

(1,005)

1,005

                 

 

 

                   

Earmarked to clear the backlog of responsive repairs and voids works.

EDB Reserves

(182)

100

(82)

 

 

(82)

Earmarked to support the EDB revenue budget of £0.184m.

Disrepair Claim reserve

(1,000)

1,000

             0  

(1,000)

1,000

                   

Reserve earmarked to fund Disrepair Claims during 2026/27. Core budget removed with reserves requirement being reviewed annually.

 

(12,844)

2,951

(9,893)

0

1,000